On Site Update - May 2025

 

We’re excited to share the latest construction update from Cocco Lagoon!

Unfortunately, the rainy season has lasted longer than expected, delaying several scheduled works. However, our team is working hard to catch up, and visible progress is being made across the entire site.

Building A is nearly complete – we’re in the final stages of furnishing and decorating the apartments. The interiors are taking shape, and the atmosphere of Cocco Lagoon is beginning to shine through.

Building B – the exterior painting is finished, and the façade is now complete. Window frames are being installed, and in the sections where windows are already in place, furniture assembly has also begun.

Building C – we’ve officially completed the structural work and received approval from the site manager to move on. We are now starting the plastering and exterior painting, and the elevator installation is underway.

Building D – floors and tiles have been laid. Electrical installations are progressing, and elevator installation is also in progress.

Building E – we’ve finished the foundation work and are preparing for the next construction phase.

Reception area – masonry work on the first floor is complete, and plastering has begun on the ground floor.

Beach Apartments – the ceiling structure has been completed, and plastering has started.

We thank you for your continued support and patience. Every step takes us closer to making Cocco Lagoon a reality!

 

Don't miss any important events

Join our newsletter!

Cocco Lagoon – the first-ever 5-star condominium hotel in the idyllic Zanzibar Archipelago, on Pemba Island.

Want to know more about us?

Visit those pages:

©2024. Cocco Lagoon. All Rights Reserved.