Construction Journal

Estimated overall progress (BoQ): ~45–50%

Construction team: 350 people

Planned hotel opening date: June 15, 2026

  • SPA

  • Amphitheatre

  • Wedding hall

  • Sports center

  • Medical center

  • Marina

  • Completion of Block C – by October 2025

  • Completion of Reception – by October 2025

  • Completion of Makuti Beach Bar – by October 2025

  • Completion of Beach Apartments – by October 2025

  • Completion of Chill Restaurant – by October 2025

  • Waterproofing tests of the main Blue Lagoon pool – by November 2025

  • Foundations of Ocean Restaurant – by November 2025

  • Installation of Ocean Restaurant kitchen – by December 2025

  • Completion and handover of Staff House – by October 2025

  • Completion of foundation works for all buildings in the complex – by October 2025

zakres prac zaplanowanych na 2025/26

Prace planowane