General Project Status: On schedule, significant progress, and several buildings completed.
Key information:
Residential blocks A, B, and D are fully completed and received Certificates of Completion (August 19, 2025).
Nakupenda Bungalows 01–02 are also fully finished.
Block C (95%), Reception (85%), Beach Apartments (85%), Chill Restaurant (80%), and Makuti Beach Bar (80%) are in the finishing stage.
The Rooftop Bar has been completed 100%.
Construction works are ongoing for blocks E, F, G, X, Waves Villas, Ocean Apartments, Ocean Restaurant, and the Blue Lagoon & Tropical River pools.
Handover procedures for investors have begun in the completed buildings.
Estimated overall progress (BoQ): ~45–50%
Construction team: 350 people
Planned hotel opening date: June 15, 2026
Ocean Restaurant: Completion progress – 15%. Planned completion date – December 2025.
Chill Restaurant: Completion progress – 80%. Planned completion date – October 2025.
Rooftop Bar: Completed.
Makuti Beach Bar: Completion progress – 80%. Planned completion date – October 2025.
Pool Bar: Not started. Works scheduled for 2026.
SPA
Amphitheatre
Wedding hall
Sports center
Medical center
Marina
Completion of Block C – by October 2025
Completion of Reception – by October 2025
Completion of Makuti Beach Bar – by October 2025
Completion of Beach Apartments – by October 2025
Completion of Chill Restaurant – by October 2025
Waterproofing tests of the main Blue Lagoon pool – by November 2025
Foundations of Ocean Restaurant – by November 2025
Installation of Ocean Restaurant kitchen – by December 2025
Completion and handover of Staff House – by October 2025
Completion of foundation works for all buildings in the complex – by October 2025