Construction Update: July 2024

Dear Clients and Followers, We are excited to share the latest progress on our construction projects. Below you will find detailed information about what we have achieved recently.

Block B: We have completed the scaffolding installation, providing safe access to all parts of the terrace. The formwork is underway, allowing precise concrete pouring according to the architectural design. 

Nakupenda 2: Ongoing work on flooring and lintel alterations is optimizing space and structural integrity of the whole building. We also have started plastering internal walls on the ground floor, an essential step towards finishing the interiors. What’s more, we’re working on marking the levels of external walls on the first floor, preparing them for plastering. 

Staff House: We continue basement backfilling, crucial for the building’s stability and further construction works.

Block C: We have commenced foundation footing casting, the first step in building a stable structure.

Block D: Ongoing column casting will form the main load-bearing elements of the building.

Block A: We have started construction on the hot tub/jacuzzi, a luxurious addition for future residents. We have begun skimming walls, preparing surfaces for painting and other finishing works.The foundation for the pool has been excavated, the first step in constructing this recreational feature.